Customer:
Utility company of the Kiev city state administration
on protection, maintenance and exploitation of lands of the water fund of Kiev “Pleso”
An object:
Building at the address: Kiev, m. Livoberezhna
A task:
Delivery of modular rooms and installation of a rescue station
Work period:
5 working days
Customer:
Eridon company
An object:
from. Pochuyki, Zhytomyr region,
Plant construction
Mobile modular campus of 40 modules (household, office, sanitary)
A task:
Delivery and installation of modular blocks in the format of an administrative building
Work period:
15 working days
Customer:
SAIL company
An object:
Preparation for the final of the Football Champions League in Kiev,
Khreschatyk street in 2018
A task:
Installation / dismantling of stages, fences, structures for the event
Work period:
30 working days
Customer:
Faber International
An object:
Construction of the first stage
SEC Rive Gauche,
Kiev, st. Zdolbunovskaya
A task:
Organization of a modular campus of 20 modules (sanitary, office, household) during the construction of a shopping and entertainment center
Work period:
2016-2019
Customer:
Sabo Group company
An object:
Building at the address: Kiev,
Kurenevsky lane, 17a
Area – 2300m², building height – 20m.
A task:
Delivery and installation of modular premises: office, household and sanitary. Installing the generator
Work period:
15 working days
Customer:
Technobud Perspective company
An object:
Building at the address: Odessa, per. Resort
LCD “Elegy Park” – 25 floors, Height 80m.
A task:
Delivery, installation and maintenance of 10 lifts Geda 1500 z / zp
Work period:
5 working days
Customer:
“Myobius” company
An object:
Modular office building, Kiev
A task:
Delivery and installation of modular premises: office, household and sanitary. Installing the generator
Work period:
15 working days
Customer:
Ackerman company
An object:
Modular administrative building
A task:
Delivery and installation of modular premises: office, household and sanitary. Installing the generator
Work period:
15 working days
Customer:
Company “GE Ukraine”
An object:
Construction of a wind farm in the Kherson region
A task:
Preparation of the foundation, installation and commissioning of wind generators, organization of water supply and electricity supply
Work period:
120 working days
Customer:
Crosco Ukraine company
An object:
Drilling site
Poltava region, 2019
A task:
Delivery of mechanisms for drilling site operation.
Work period:
60 working days
Customer:
Sabo Group company
An object:
Reconstruction of the building facade
Kiev, Kurenevsky lane
A task:
Delivery and installation
scaffolding on the building.
Area – 3000m², building height – 20m.
Work period:
15 working days
Customer:
“Vestas Ukraine” company
An object:
Construction of a wind farm in the Kherson region, Mirnoye village, 2019
A task:
Unloading / installation of elements of wind turbines
Work period:
60 working days
Customer:
BK FIDELIS company
An object:
Construction of a multi-storey building Kiev,
Podolsky district, 2020
A task:
Formwork installation
during the construction of a parking lot in a multi-storey building.
Work period:
15 working days